MAIN ST. WATER & SEWER IMPROVEMENTS - SCHEDULE STATUS UPDATE 6/2023

Project Status

MAIN STREET WATER AND SEWER IMPROVEMENTS - Schedule Status Update 6/2023 


Main Street Phase I - Water Improvements 
Highland St. to Warren St. & Warren to Russell (April-July)

  • Temporary Water Main (April-May) (COMPLETE)
  • Perimeter Valving April (April) (COMPLETE)
  • Water Main Installation (May-June) (IN PROGRESS)
  • Service Connections (June-July) 

Main Street Phase II - Water Improvements 
End of Old N. Main St. - RR Casing Installation (April) (COMPLETE)
Foster St. to Old N. Main St. Directional Drill (June)

Highland St. to Rt. 175A Rotary (April-October)

  • Temporary Water Main (September)
  • Perimeter Valving (April) (COMPLETE)
  • Water Main Installation (September-October)
  • Service Connections (October)

Rt. 175A Rotary to Old North Main (April-August)

  • Temporary Water Main (April-May) (COMPLETE)
  • Perimeter Valving (April) (COMPLETE)
  • Water Main Installation (July-August)
  • Service Connections (August)

Old North Main St. (April-June)

  • Temporary Water Main (May) (COMPLETE)
  • Perimeter Valving (April) (COMPLETE) 
  • Water Main Installation (May-June) (IN PROGRESS) 
  • Service Connections (June-July) 

Main Street Phase II - Sewer Improvements (Apirl-August)
End of Old N. Main St. - RR Casing Installation (April) (COMPLETE)

Rt. 175A Rotary to Tobey Rd. Gravity Sewer (May-July) (IN PROGRESS)

End of Old N. Main St. Force Main Installation (July)

Main St. & Green St. Pipe Lining & Manhole Rehabilitation of Existing Sewer (April-October) (IN PROGRESS)


Town - S. Main St. Drainage Contract (June-September)


Main St. & Old N. Main St. - Roadway & Sidewalk Restoration (Spring 2024)