MAIN STREET WATER AND SEWER IMPROVEMENTS - Schedule Status Update 6/2023
Main Street Phase I - Water Improvements
Highland St. to Warren St. & Warren to Russell (April-July)
- Temporary Water Main (April-May) (COMPLETE)
- Perimeter Valving April (April) (COMPLETE)
- Water Main Installation (May-June) (IN PROGRESS)
- Service Connections (June-July)
Main Street Phase II - Water Improvements
End of Old N. Main St. - RR Casing Installation (April) (COMPLETE)
Foster St. to Old N. Main St. Directional Drill (June)
Highland St. to Rt. 175A Rotary (April-October)
- Temporary Water Main (September)
- Perimeter Valving (April) (COMPLETE)
- Water Main Installation (September-October)
- Service Connections (October)
Rt. 175A Rotary to Old North Main (April-August)
- Temporary Water Main (April-May) (COMPLETE)
- Perimeter Valving (April) (COMPLETE)
- Water Main Installation (July-August)
- Service Connections (August)
Old North Main St. (April-June)
- Temporary Water Main (May) (COMPLETE)
- Perimeter Valving (April) (COMPLETE)
- Water Main Installation (May-June) (IN PROGRESS)
- Service Connections (June-July)
Main Street Phase II - Sewer Improvements (Apirl-August)
End of Old N. Main St. - RR Casing Installation (April) (COMPLETE)
Rt. 175A Rotary to Tobey Rd. Gravity Sewer (May-July) (IN PROGRESS)
End of Old N. Main St. Force Main Installation (July)
Main St. & Green St. Pipe Lining & Manhole Rehabilitation of Existing Sewer (April-October) (IN PROGRESS)
Town - S. Main St. Drainage Contract (June-September)
Main St. & Old N. Main St. - Roadway & Sidewalk Restoration (Spring 2024)