TWO-WEEK OUTLOOK
MAIN STREET WATER AND SEWER IMPROVEMENTS / DOWNTOWN DRAINAGE IMPROVEMENTS
PLYMOUTH VILLAGE WATER AND SEWER DISTRICT / TOWN OF PLYMOUTH, NEW HAMPSHIRE
Week of the 29th Week of the 5th
CREW 1 North Main Street – Sewer North Main Street - Sewer
CREW 2 South Main Street – Water South Main Street - Water
CREW 3 Old N. Main Street – Water South Main Street - Drainage
CREW 4 Detention Pond Detention Pond
Anticipated work for the week of May 29, 2023: (10-hr days 7AM-5PM)
MONDAY - 5/29/23
CREW 1: NO WORK MEMORIAL DAY
CREW 2: NO WORK MEMORIAL DAY
CREW 3: NO WORK MEMORIAL DAY
TUESDAY - 5/30/23
CREW 1: Sewer Main Line installation at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Pearl Street and the Main/High Street Rotary.
-Manhole installation starting at MH-008 Progressing to MH-007 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Install at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Water Main Installation on Old North Main Street
-Road closed to local traffic only
-Delay to be expected entering and exiting Old North Main Street
CREW 4: Continue work at the detention pond.
WEDESDAY - 5/31/23
CREW 1: Sewer Main Line installation at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Install at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Water Main Installation on Old North Main Street
-Road closed to local traffic only
-Delay to be expected entering and exiting Old North Main Street
THURSDAY - 6/1/23
CREW 1: Sewer Main Line installation at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Install at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Water Main Installation on Old North Main Street
-Road closed to local traffic only
-Delay to be expected entering and exiting Old North Main Street
FRIDAY - 6/2/23
CREW 1: Sewer Main Line Paving at Main Street and High Street Rotary progressing towards Tobey Road for work installing MH-007 Progressing to MH-429.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Paving for work at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Water main paving for work on Old North Main Street
-Road closed to local traffic only
-Delay to be expected entering and exiting Old North Main Street
Preliminary work for the week of June 5, 2023: (10-hr days 7AM-5PM)
MONDAY - 6/5/23
CREW 1: Sewer Main Line installation at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-Traffic on Pearl Street will be closed off to Main Street, Traffic will utilize Weeks and Merrill Street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Install at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Drainage installation from the detention pond progressing towards Warren Street.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
- Potential traffic detour for Main Street and Warren Street. South bound traffic will be diverted to Warren-Thurlow-Parker Street. North bound traffic will be diverted to Parker-Thurlow-Warren Street
CREW 4: Continue work at the detention pond.
TUESDAY - 6/6/23
CREW 1: Sewer Main Line installation at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-Traffic on Pearl Street will be closed off to Main Street, Traffic will utilize Weeks and Merrill Street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Install at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Drainage installation from the detention pond progressing towards Warren Street.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
- Potential traffic detour for Main Street and Warren Street. South bound traffic will be diverted to Warren-Thurlow-Parker Street. North bound traffic will be diverted to Parker-Thurlow-Warren Street
CREW 4: Continue work at the detention pond.
WEDESDAY - 6/7/23
CREW 1: Sewer Main Line installation at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-Traffic on Pearl Street will be closed off to Main Street, Traffic will utilize Weeks and Merrill Street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Install at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Drainage installation from the detention pond progressing towards Warren Street.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
- Potential traffic detour for Main Street and Warren Street. South bound traffic will be diverted to Warren-Thurlow-Parker Street. North bound traffic will be diverted to Parker-Thurlow-Warren Street
THURSDAY - 6/8/23
CREW 1: Sewer Main Line installation at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-Traffic on Pearl Street will be closed off to Main Street, Traffic will utilize Weeks and Merrill Street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Install at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
-As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Drainage installation from the detention pond progressing towards Warren Street.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
- Potential traffic detour for Main Street and Warren Street. South bound traffic will be diverted to Warren-Thurlow-Parker Street. North bound traffic will be diverted to Parker-Thurlow-Warren Street
FRIDAY - 6/9/23
CREW 1: Sewer Main Line Paving at Main Street and High Street Rotary progressing towards Tobey Road.
-Work will be on Main Street between Merrill Street and the Main/High Street Rotary.
-Manhole installation starting at MH-007 Progressing to MH-429 North of the Rotary.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
-Anticipated traffic detour from the Main/High Street Rotary around Highland/Langdon Street to Merrill for North bound traffic. In addition, traffic flowing South to the rotary will be detoured from Merrill/Langdon Street to highland street.
-Traffic on Pearl Street will be closed off to Main Street, Traffic will utilize Weeks and Merrill Street.
-The Detour for South bound will be altered to Tobey Road and Weeks Street if traffic at Merrill Street becomes too congested under direction of the Police Chief.
CREW 2: Water Main Paving for work at Highland Street progressing to Warren Street.
- Work will be on Main Street between Railroad Square Road and Warren Street.
- As the crew progresses South down Main Street, Parking will be taking on both sides depending on location of the work to allow for alternating traffic around the excavation and water main installation.
CREW 3: Drainage installation from the detention pond progressing towards Warren Street.
-Detours May Apply or Alternating Traffic, Local Police and Fire Notified Daily.
- Potential traffic detour for Main Street and Warren Street. South bound traffic will be diverted to Warren-Thurlow-Parker Street. North bound traffic will be diverted to Parker-Thurlow-Warren Street